Having completed the successful controlled piecemeal demolition of two 320ft reinforced concrete chimneys at Sabic Chemicals in Teeside during 2019, Churchill have now started work on the last and tallest of three structures that they are contracted to complete.
Upon completion of preparatory work and the installation of Churchill’s chimney dismantling rig, this last chimney will start to slowly disappear from the skyline from the beginning of December 2019 onwards.
Work will continue through the winter months with completion be achieved by March 2020. For more information on this project and the 100+ similar projects Churchill have completed using their specialised rig, please call us on 0844 504 9998.